

The peak of the back-ups and associated crashes typically extends from around 6:30 AM to around 8:30 AM, although as yearly traffic volumes grow the peak period will continue to expand as drivers leave earlier or later to avoid most of the delays. The back-ups typically extend to the York County line (at the Yellow Breeches Creek) and beyond, often reaching the PA Turnpike Interchange. The northbound back-ups also are becoming worse during the afternoon commute. Concerning crashes, a large volume of collisions occur at relatively low speeds, and since they do not involve injuries or towed vehicles with police intervention, they are not reportable crashes. As a result, the majority of crashes are not reported, so the crash statistics are unavailable. Another frequent site of rear-end collisions is at the southbound I-83 on-ramp from PA 581 eastbound. There is an extremely short acceleration
lane because of the limiting Lowther Street Bridge opening, and combined with limited sight distance, results in frequent collisions when the drivers find out too late that the vehicle in front of them has not moved into the travel lane.
![]() |
Northbound I-83 traffic in the morning peak period typically backs up beyond Limekiln Road, a distance of two miles. |
This chronic congestion and safety situation at this interchange has resulted in PennDOT taking steps to correct the main problems with an early action safety solution, which is not the total interchange reconstruction featured in the I-83 Master Plan, but instead one that can be designed and constructed in the near future using available roadway funds. The process has already begun. In 2009, PennDOT closed the Brandt Street on-ramp that, even with low traffic volumes, caused operational problems of vehicles abruptly accelerating and changing lanes. The ramp has been gated and is available only to emergency vehicles. PennDOT is coordinating with the emergency service providers in the surrounding municipalities during the design process to assure that the access that is proposed for the early action project will meet their needs.
![]() |
The Brandt Avenue ramp to I-83 northbound and PA 581 westbound was closed in 2009. The Lowther Street Bridge over I-83 will be replaced with a wider bridge to accommodate more lanes. |
The main component of the proposed project is to maintain two continuous lanes of traffic on I-83 northbound through the interchange.
Click to view existing and proposed local ramp access
There are not anticipated to be any displacements of residences or commercial facilities as a result of this project, although minor property acquisitions will be required to accommodate the additional lanes.Preliminary design and environmental clearance have been completed with FHWA approval of the environmental document, a Categorical Exclusion Evaluation (CEE) Level 2, on June 15, 2011.
Schedule of Project Activities:A public meeting
was held for the I-83 / PA581 Interchange Bottleneck Safety Project on April 13, 2011
(Click here for meeting
highlights)
(Click here for public meeting comments and responses)